Progress of the Outstanding Construction Works of the Library Extension & Revitalisation (LER) Project
Outstanding Construction Works |
Planned Construction Period |
Completion Status |
Construct new top floor and IAQ works |
Aug 2020 – Apr 2022 |
In Progress |
Internal bridges 3/F - 5/F |
May – Sept 2021 |
Extended to mid 2022 |
1/F South Wing |
May – Aug 2021 |
Completed in Dec 2021* |
P/F - counter, stack space and staircase no. 2 lobby |
Dec 2021 – early Apr 2022 |
Extended to June 2022 |
G/F South Wing |
Dec 2021 – early Apr 2022 |
Extended to June 2022 |
G/F North Wing and 3/F |
May – Aug 2022 |
In Progress |
P/F and main entrance |
May – Oct 2023 |
|
*Defects rectification in progress.
Major noisy works will be suspended during revision & examination period.
For enquiries about progress of construction works, please contact Project in charge of the Campus Development Office, Mr. John Lai at Tel.: 2766-7887 or CDO Hotline: 2766-7766, Email: cdinfo@polyu.edu.hk.
The LER project has commenced in late July 2020 and the target date of completion is the 4th quarter in 2023. Here is a timeline of the major works taking place during this period.